|
By Mitchell Oakley
LITTLEFIELD — Sewerage spills at the N.C. 11
pump station have been frequent during the past year. And, because
of them, the Towns of Ayden and Winterville were notified by the
North Carolina Division of Water Quality they would be put under a
sewer moratorium on July 5, 2004.
The Town of Ayden has worked for five years in
an effort to get grant money to replace aging sewer lines in town.
Aged lines, no doubt, contributes to the inflow and infiltration
issues that cause ground water to get into sewage.
Mayor Steve Tripp pointed out in an interview
that the heavy rains of the past year — 27 inches more rainfall than
usual — have gotten into the deteriorating lines, including the 2.1
miles of CMSD concrete line that has deteriorated rapidly of late.
Tripp says however that the spills are being
treated on site. “When it does happen at the site it is treated at
the site. It is certainly not the preferred method, and is something
we will fix.”
Ayden began five years ago trying to get
funding assistance from Construction Grants and Loans with the
Division of Water Quality. (DWQ).
Ayden was twice turned down for a grant for
sewer line replacement, first in March 1999 and again in September
1999 when the first grant was reconsidered.
Ayden’s engineering firm, McDavid & Associates
were told that Ayden was not scoring as well as other projects based
on criteria established by the agency. Tripp said the engineering
firm met with representatives of Construction Grants and Loans with
DWQ. It was recommended that a joint grant, between the town and the
Contentnea Metropolitan Sewerage District (CMSD) be applied for that
would include Ayden’s replacement of sewer line and a reuse project
for the CMSD.
The grant was applied for March 30, 2001 and
awarded June 12, 2001 in the amount of $3 million. A total of
$400,000 would be used for the CMSD project with the balance going
to Ayden to replace old sewer lines down Third Street. Because of
that project the state has refused to pave Third Street until the
work is done.
Despite the award, however, the project has
been delayed time and again. It took DWQ nine months to review the
first plan comments. Because of hydro geologic concerns with
the spray irrigation field (the CMSD reuse
project), there were more delays that kept Ayden from helping solve
some of the CMSD’s inflow and infiltration problems.
DWQ eventually agreed in March to allow Ayden
to proceed with its sewer project despite the fact the reuse project
is still in limbo.
Ayden moved immediately to get the project
underway. In April they authorized the receipt of bids and received
bids in May. Ayden Town Manager Adam Mitchell reported last week
that those bids came in $900,000 higher than expected, probably due
in part to the length of time that elapsed from DWQ approval of the
grant and the actual bidding of the project.
Tripp said the town will have to change the
scope of the project in order to use the $2.6 million in funds that
are allocated. That means less aged sewer lines will be replaced and
less help to the CMSD lift station on N.C. 11.
“We’ve been working on this project for five
years,” Tripp said. “We’ve always had a commitment to solve our
inflow and infiltration issues. From the time we were awarded the
funds it has taken two years and 8 months to go through the hoops of
getting permitted. We will continue our efforts to solve these
issues as quickly as the state will allow us to.”
|